The project consisted of removal of deteriorated hardstands, remediation of soft spots, meticulous proof rolling, and compaction of the subgrade to accommodate the new 2800m2 post-tensioned slab on the ground, catering to the demands of the heavy industrial container yard. Additionally, the fire ring main underwent upgrades as part of the project.
facture. initially offered guidance on local market procurement for the project before assuming the role of Superintendent's Representative and Clerk of Works during the construction phase.